Sea Grant Law Center & MS/AL Sea Grant Legal Program
 

Please update your links! Our new website url is http://masglp.olemiss.edu . This old website will soon cease to exist!

FERC Approves Natural Gas Pipeline through
Gulf Marine Habitat

David N. Harris, Jr., 2L


On February 22 the Federal Energy Regulatory Commission (FERC) granted approval to Gulfstream Natural Gas Pipeline, L.L.C. for construction of a 744 mile natural gas pipeline in the Gulf of Mexico.1 The pipeline will stretch from the southern tip of Mississippi and Alabama to Florida crossing through Gulf of Mexico essential fish habitat and marine reserve areas.2 The pipeline will supply natural gas to sites of future gas powered electric generation plants planned to meet Florida population growth over the next 30 years. Gulfstream plans to begin construction in June after submitting mitigation plans to counter damage to the marine environment in the Gulf.


Determining the Effects on Habitat
To meet the statutory requirements of planning the pipeline, Gulfstream conducted an Environmental Assessment (EA) to comply with the National Environmental Policy Act (NEPA). The EA described the scope and identified significant impacts on the environment. Because the EA found that the project will have significant effects on the environment, Gulfstream prepared an Environmental Impact Statement (EIS) to assess, among other items, the effects on Essential Fish Habitat (EFH) designated for federally-managed species in the Gulf.


EFH is defined as “those waters and substrate necessary for spawning, breeding, feeding, or growth to maturity”3 and actions having potential adverse effects on EFH require an impact analysis. In 1999, the Gulf of Mexico Regional Fishery Management Council and the National Marine Fisheries Service designated the majority of the Gulf of Mexico as EFH. Because the pipeline will traverse EFH, Gulfstream was required to conduct an EFH analysis to supply (1) a description of the action, (2) an identification of direct, indirect, and cumulative impacts, (3) the effects of the action on EFH, and (4) a proposal for mitigation of adverse effects. The analysis concluded that 25 of 27 species in the area will face some sort of adverse impact through the construction, operation, and maintenance of the pipeline. Gulfstream must also determine the adverse effects on areas containing prey species to determine the impairment placed on these species to act as food sources.


Pipeline Construction and its Impacts
To install the pipeline underwater, a remote operated sled will excavate a trench with high pressure air and water jets. In shallow water installation, divers will create trenches using hand-held jets. Finally, barges and other support vessels will install the pipeline while anchored above the excavation site.


Excavation. The majority of impacts result from the excavation process required to install the pipeline. The first widespread impact originates from sedimentation and turbidity from the jetting process: an estimated 2886 acres of sea bottom will be affected.4 By increasing the suspended material in the water column, eggs and larva of demersal and pelagic fish species may face substantial mortality rates. Adult species may encounter less adverse impact because projections assume they will avoid the construction area. Along with the effects on eggs and larva, the hard bottom and soft bottom communities will face impairment and destruction from the jetting process.


Installation. The second widespread impact occurs from the anchoring and cable sweeping related to the installation of the pipeline. Anchoring barges used to install the pipeline leave anchor scars on the sea floor which remain after an anchor is removed from the sea bottom. As a result, the hard bottom and soft bottom communities are destroyed or severely impaired from anchor placement. Each “anchor footprint” affects a 320 square foot area of bottom habitat that is essential to support reef fisheries. These “footprints” cumulatively affect 60 acres of bottom habitats.5


Furthermore, cable sweeps occur when cable attached to anchors drag across the sea bottom. These sweeps disturb and may destroy live fauna and breeding grounds for fish species. This impact is by far the greatest single impact on EFH. The estimated area affected is over 46,068 acres of hard bottom and 5,950 acres of live soft bottom habitat.6 The installation and excavation effects occur simultaneously.


Maintenance and Recovery. Gulfstream estimates 32 acres of live and hard bottom habitat impacts for the actual pipeline.7 The U.S. Department of Transportation and the Minerals Management Service require a pipeline in less than 200 feet of water to be covered by 3 feet of soil or bottom particulate. Periodic pipeline inspections must occur in these areas in order to monitor earthen cover of the pipeline. These inspections cause minimal adverse effects on the habitat as compared with the other more wide spread impacts occurring from the excavation and installation process.


Gulfstream estimated the recovery periods to range from temporary impacts (day to weeks to recover) to permanent impacts (more than 20 years to recover). The sedimentation and turbidity is expected to be a temporary impairment but the anchoring and cable sweeping will likely cause permanent damage to the habitat’s live fauna and substrate. The impacts to the hard and live bottoms habitats will also adversely affect prey species that act as food sources for federally managed fish species.


Mitigation of Effects on EFH
After reviewing the adverse effects from the EFH analysis, the FERC incorporated these considerations by making the approval of Gulfstream’s certificates conditional upon mitigation. Generally, Gulfstream must avoid EFH wherever possible. To accomplish this, the FERC requires Gulfstream to follow very specific mitigation measures. For example, Gulfstream cannot conduct construction activities in the grouper marine reserve at Steamboat Lumps during the gag grouper spawning time (January through May).8


Furthermore, Gulfstream must develop and implement a plan to monitor hard bottom and live bottom impacts resulting from the construction process. The plan must be completed and approved prior to the beginning of construction activities. Developed in consultation with the Minerals Management Service and the National Marine Fisheries Service, the plan will provide monitoring of activities that include pipeline trench, anchor strike and cable sweep areas.


In order to limit the damage that occurs due to anchor strikes and cable sweeps, Gulfstream will use digital global positioning systems and geographically referenced digital maps of hard bottom areas to aid in the placement of anchors. The anchor placement must avoid hard bottom impact when possible. To aid in the monitoring study, Gulfstream will supply an “as built” anchor plat showing the location of all anchor strikes that impact the delineated hard bottom areas.9
Finally, Gulfstream has contributed at least $350,000 in the Gulfstream Environmental and Recreational Trust Program to grant awards to projects demonstrating community and environmental need, especially for projects that are near the pipeline route. This program is scheduled to begin once the construction for the pipeline has commenced and continue for five years after operation has begun.10


Conclusion
The adverse effects caused by the construction and installation activities along the route of the pipeline pose substantial impacts to EFH and areas designated as unique marine reserve habitat. The FERC has determined that Gulfstream has made attempts to mitigate the impact of the pipeline on these areas in the Gulf but is requiring additional mitigation measures in order to insure that effects on the environment are minimal. This project demonstrates the responsibility placed upon proposed projects that may adversely affect EFH to establish plans and alternatives that will minimize that adverse effect.

Endnotes:
1. Originally, Gulfstream was one of two competing pipeline proposals. Buccaneer Gas Pipeline Company (“Buccaneer”) proposed the other. During the last few months, because of corporate mergers, The Williams Companies and Duke Energy Corporation acquired 100 percent membership interests in Gulfstream on February 8, 2001. With the purchase of Gulfstream, the company that was further along in the permitting process, the Buccaneer proposal was abandoned. The Buccaneer pipeline was likely to have greater adverse impacts on essential fish habitat and marine reserves in the Gulf.
2. FERC Order issuing Certificates. 94 FERC 61,185 (2001) at 12 (on file with editors).
3. 16 U.S.C. § 1802(10) (2001).
4. ERC Draft Environmental Impact Statement. FERC Docket No. CP00-06-000, pg. 5-7 (On file with editors).
5. Id.
6. Id.
7. Id.
8. See. 94 FERC 61,185 at 22.
9. Id.
10. For more information from Gulfstream, visit www.gulfstreamgas.williams.com.


Report any problems or broken links to Webmaster
University of Mississippi

 

FERC Approves Natural Gas Pipeline through
 

Phone (662) 915-7775 • Fax (662) 915-5267 • 256 Kinard Hall, Wing E, University, MS 38677-1848

Please report any broken links or other problems to the Webmaster         Site Map        Opentracker.net: Web Site Statistics

University of Mississippi