| |
Please update your links! Our new website url is http://masglp.olemiss.edu . This old website will soon cease to exist!
Court
Grants No Leniency for Maritime Lien Claim
Sweet Pea
Marine, LTD. v. APJ Marine, Inc., 411 F.3d 1242 (11th Cir. 2005)
Jonathan
P. Lew, 2L, Roger Williams University School of Law
In June the U.S. Court of Appeals for the Eleventh Circuit refused to
apply a maritime lien to a yacht after a contract dispute, finding that
such liens encumber commerce and should be strictly construed. In a
case involving the remodeling of the yacht Sweet Pea, the court found
that the party enforcing the lien failed to prove that the prices it
was charging the vessel owner for products were reasonable. This reasonable
price element was also necessary to prove the breach of a maritime contract
claim, which failed as well.
Background
Sweet Pea Marine, Ltd. (Sweet Pea) contracted with APJ Marine, Inc.
(APJ), to outfit and remodel the 127-foot pleasure yacht Sweet Pea.
The contract included pay scales for labor, including skilled laborers
at $56/hour, semi-skilled laborers at $36/hour, and unskilled laborers
at $26/hour. In addition, the contract authorized APJ to add a 15 percent
mark-up to the cost of materials and supplies bought for the job. Problems
arose when Sweet Pea discovered that unskilled workers were used and
billed as skilled workers at a much higher cost. As a result, Sweet
Pea terminated the contract in November 2001. In March 2002, APJ sent
Sweet Pea a bill for outstanding costs; Sweet Pea refused to pay and
this lawsuit commenced.
Sweet Pea filed a complaint in federal court against APJ for breach
of contract, negligent misrepresentation, fraud, and breach of fiduciary
duties. APJ responded, claiming breach of an oral maritime contract
and requesting a maritime lien be placed on the Sweet Pea. The district
court found for APJ and awarded the company $244,000 for the 15 percent
mark-up for goods and materials it purchased. The district court also
imposed a maritime lien on the vessel in the same amount.
On appeal, the Eleventh Circuit reversed the district courts holding
for APJ, finding that the company failed to prove that the prices it
paid for the marked-up materials were reasonable. According to the court,
by granting APJs claims the district court overlooked the reasonable
price element, which is essential to both the breach of contract claim
and the maritime lien.
Maritime
Lien Claim
The Federal Maritime Lien Act provides a maritime lien on a vessel to
a person that provides necessaries at a reasonable price to a vessel
if the services are maritime in nature and facilitate the vessels
use in navigation or maritime commerce.1 Here,
APJs contract to remodel the Sweet Pea is sufficient because there
is no question that necessaries as defined in the Federal Maritime Act
specifically include vessel repairs.2 However,
APJ failed to prove that the materials it purchased for remodeling the
Sweet Pea were purchased at a reasonable price.
The Eleventh Circuit viewed the district courts judgment as clearly
erroneous because APJ failed to prove that the prices it had paid
for materials used on the Sweet Pea were reasonable according to industry
custom and in accord with prevailing charges for the work done and the
materials furnished.3 APJ did not present any evidence
to show that the prices submitted to Sweet Pea were reasonable. In its
defense, APJ argued that Sweet Pea waived its ability to contest reasonableness
by agreeing to the 15 percent mark-up on materials purchased. But the
circuit court found this argument unpersuasive because an agreement
to a mark-up does not indicate a reasonable price. Even though the 15
percent mark-up may be standard for the industry, this fact alone did
not establish that the underlying prices were reasonable. Moreover,
testimony that the labor rates used were industry standard also had
no bearing on the reasonableness for the prices of the goods and materials.
Thus, without any direct evidence of reasonable price (such as testimony
that the price paid by APJ was industry standard for goods) the Eleventh
Circuit refused to award APJ the maritime lien.
Maritime
Contract Claim
The reasonable price element was essential to both of APJs maritime
claims. For APJ to recover on its claim that an oral contract regarding
the repair of a vessel was breached it had to prove the terms of the
maritime contract, the breach, and the reasonable value of the purported
damages.4 Consequently, APJs failure to prove
reasonable price had a conclusive effect on its maritime lien claim.
Diversity
of Jurisdiction
Finally, the court found that jurisdiction in the federal district court
was proper. APJ invoked admiralty jurisdiction when it claimed its oral
contract with Sweet Pea was breached. The U.S. Constitution grants federal
courts original jurisdiction in all civil cases involving admiralty
or maritime jurisdiction.5 A maritime contract is defined
to be one having reference to commerce or navigation. The particular
element essential to give it a maritime character is direct connection
with commercial transactions or navigation.6 Because
APJs contract involved the repairing of the Sweet Pea, the admiralty
jurisdiction requirement was met.7
Conclusion
Maritime liens were created to grant a vessel credit in order for her
to complete her voyage; thus the lien was created for the benefit of
the vessel, not the benefit of the creditor.8 The completion
of her voyage remained paramount to any individual debt a vessel might
accrue.
Here, the Eleventh Circuit strictly construed the Federal Maritime Lien
Act because the maritime lien was not offered as credit to Sweet Pea
so it could continue on its voyage. Rather, the lien acted as an insurance
policy for APJ so the company could be guaranteed compensation. APJs
failure to proffer any direct evidence in regard to the reasonable price
element of both maritime claims was clearly erroneous and granting an
award and a maritime lien would impede the vessels ability to
participate in commerce.
ENDNOTES
1. 46 U.S.C. § 31342; E.S. Binnings, Inc. v. M/V
Saudi Riyadh, 815 F.2d 660, 666 (11th Cir. 1987).
2. Boland Marine & Mfg. Co., Inc. v. M/V HER
AN, 1998 U.S. Dist. LEXIS 6809 (D.La. 1998).
3. Ex parte Easton, 95 U.S. 68, 77 (U.S. 1877);
Shelley Tractor & Equip. Co. v. The Boots, 140 F.Supp. 425,
426 (E.D.N.C. 1956).
4. See Exxon Corp. v. Cent. Gulf Lines, Inc.,
500 U.S. 603, 605-06 (U.S. 1991).
5.
U.S. Const. art. III, § 2, cl. 1.
6.See Hatteras of Lauderdale, Inc. v. Gemini Lady,
853 F.2d 848, 850 (11th Cir. 1988).
7.Repair of a ship is distinguished from construction
of a ship because until a vessel is completed and launched it does not
become a ship in the legal sense and cannot become in direct connection
with commercial transactions or navigation. Id.
8. In re Hydraulic Steam Dredge, 80 F. 545 (7th
Cir. 1897).
Court Grants No Leniency for Maritime Lien Claim
|
|