| |
Conservation
Group Finds Itself Up FERCs River Without a Paddle
National Comm.
for the New River, Inc. v. Federal Energy Reg. Commn., 2005 WL 3440696
(D.C. Cir. Dec. 16, 2005)
Emily
Plett-Miyake, 3L, Vermont Law School
The National Committee for the New River, Inc. (NCNR), an environmental
group, petitioned for review of the Federal Energy Regulatory Commissions
(FERCs) rejection of seven of its claims that a natural gas company
had failed to comply with conditions imposed on a pipeline construction
project. The Court of Appeals for the D.C. Circuit dismissed NCNRs
petition, stating that the group lacked standing to challenge the companys
conduct.
Background
In 2001, the East Tennessee Natural Gas Company (East Tennessee) petitioned
FERC for permission to extend its natural gas pipeline, based in Tennessee,
by about ninety-four miles, from Virginia to North Carolina. In 2002,
FERC issued East Tennessee a certificate of public convenience and necessity
for the proposed extension, known as the Patriot Project.
The certificate was subject to sixty-nine conditions, pursuant to Section
7 of the Natural Gas Act.1 The conditions involved
a wide range of issues relating to the pipelines construction,
including minimization of project impacts on the southern population
of the bog turtle, ten-day deadlines for cleanup after trenches are
backfilled, the filing of certain documents, including weekly status
reports, with FERC, and terms by which changes to the project proposal
would be allowed.
NCNR is an environmental group devoted to protecting the New River,
which is located in North Carolina and southwest Virginia. NCNR has
been involved in fighting the Patriot Project proposal since
the initial certification proceedings, including participation as an
intervenor in a losing challenge. NCNR continued to mount legal challenges
against East Tennessee, and as of the time of this appeal had filed
nearly twenty adversarial pleadings since the certification of the project.
The particular pleading before the court here addressed seven of the
FERC orders involving five of the legal issues arising from those pleadings.
The appeal of the orders claimed that East Tennessee failed to live
up to the conditions of certification.
Court
Decision
The court discussed each of the appeals of the seven FERC orders in
turn. NCNRs primary claim, and the subject of four of the orders
and two rehearings, was that East Tennessees route realignments
were unauthorized because they varied too far from the original route
that FERC had certified.
The court declined to evaluate these claims on their merits because
it found that NCNR lacked standing to bring the challenge. In making
this determination the court noted that [a]esthetic and environmental
harms may confer Article III standing if they describe a concrete and
particularized injury in fact that is actual or imminent, causally linked
to the conduct at issue, and redressable by the relief requested.2
The court found that the harms alleged by the plaintiffs did not meet
this standard. The court noted that the allegations were not sufficient
and focused on the general harms that would arise as a result
of construction.3 The court said that NCNR must
demonstrate that its members have suffered, or will suffer, specific
environmental and aesthetic harms as a result of the route realignments
themselves.4 The court found that the affidavits
submitted by NCNR did not explain such a particularized injury. NCNR
raised similar issues and showings of proof in challenges to the initial
certification. The court noted that our earlier decision permitted
the pipeline to be built, so general harms stemming from construction
[or realignment] of a pipeline do not confer standing for this lawsuit.5
NCNR raised four additional issues. The first was whether East Tennessees
prior effort to drill under the New River should have been declared
a failure under Condition 22 of the FERC certificate, which
would have allowed East Tennessee to abandon drilling in favor of a
better site.6 The court declared that this condition
conferred no right upon NCNR. The court further found that the issue
was moot, as the pipeline resulting from the drilling had been in operation
for over two years, and that having succeeded, the drilling effort
patently was not a failure.7
The second additional issue was procedural, with NCNR arguing that it
was entitled to service of documents by East Tennessee after certification.
The court disagreed, and found that NCNR had no such procedural right.
As explained by FERC, its rules do not require that all parties
to a certification be served with documents after certification is finished.8
Finding that there was no procedural right to post-certification service,
the court ruled that NCNR had no standing to bring this particular challenge.
The third additional issue was another procedural claim, in which NCNR
argued that a FERC order was invalid because it was not signed by the
Director of the Office of Energy Projects, but rather by the Deputy
Director. The court dismissed this claim as frivolous, noting that signing
responsibilities can be delegated to specified officials in the same
office. NCNR failed to articulate what interests it believed were at
risk, and the court declined to believe that such action was that of
a rogue deputy acting surreptitiously against the Directors
will.9
The final issue raised was NCNRs appeal of a FERC order rejecting
the claim that East Tennessee failed to consider a particular route
alternative. The court noted that these issues had been raised and settled
in previous appeals, and declined the invitation to look at them again.
Conclusion
Rejecting all of NCNRs claims, the court found that the group
lacked standing to bring many of the issues, and had failed procedurally
against others. The court therefore lacked jurisdiction and dismissed
the petition for review.
ENDNOTES
1. 15 U.S.C. §717f
2. National Comm. for the New River, Inc. v. Federal
Energy Reg. Commn., 2005 WL 3440696 at *2 (D.C. Cir. Dec. 16, 2005)
(citing Lujan v. Defenders of Wildlife, 504 U.S. 555, 560-561 (1992)).
3. Id.
4. Id..
5.
Id.
6. Id.
7.
Id..
8. Id. at *3.
9. Id.
|
|