| |
Federal
Court Holds Wetlands Mitigation Not a Taking
Norman v. U.S.,
429 F.3d 1081 (Fed. Cir. 2005)
Gerald
Woodward, 3L, Stetson University College of Law
The U.S. Court of Appeals, Federal Circuit has upheld a federal claims
court ruling that the actions of the U.S. Army Corps of Engineers in
conditioning the grant of a permit to impact wetlands on a Corps-approved
mitigation plan was not an unconstitutional taking of the landowners
property without compensation. The mitigation plan provided for the
creation or restoration of other wetlands on the same site as those
that could be filled under the permit. Approval of the permit had been
sought, and this appeal subsequently commenced, by the developers of
a 2,280-acre property in Reno, Nevada.
Background
In 1986 the Southmark Corporation purchased a 2,425-acre property in
Reno, Nevada called the Double Diamond Ranch. Southmark intended to
develop the property as commercial and industrial office space. Toward
that end it prepared a master development plan and submitted it to the
Reno City Council for approval.
In early 1987 the city council gave preliminary approval to the plan
and specified a number of conditions for a grant of final approval.
One of these was the requirement for a wetlands delineation approved
by the U.S. Army Corps of Engineers.
The following year, Don Roger Norman and Roger William Norman entered
into an agreement with Southmark to purchase a 470-acre portion of the
former Double Diamond Ranch property. The Normans intended to develop
the tract for commercial use in accordance with Southmarks master
plan. At about the same time another buyer, Robert Helms, purchased
nearly all of the balance of the former ranch property from Southmark.
In September of 1988 the Corps issued a wetlands delineation for the
property now substantially owned by Helms and the Normans. It identified
a total of twenty-eight acres of jurisdictional wetlands on the property.
However, the Environmental Protection Agency (EPA), the U.S. Fish and
Wildlife Service, environmental groups and the general public uniformly
criticized the delineation as inadequate. The Corps subsequently revoked
it and in 1991 issued a new delineation developed under revised criteria.
The new delineation identified a total of 230 acres of jurisdictional
wetlands.
Three years later Helms went bankrupt and the Normans purchased his
1,800 acres from the bankruptcy estate. The Normans then developed a
new three-phase master plan that included commercial and residential
development. They applied to the Corps for a permit under section 404
of the Clean Water Act to impact fifteen of the 230 acres of delineated
wetlands on the property. The permit was granted subject to mitigation
in the form of new wetlands creation.
In 1998 the Normans filed for another 404 permit, this time seeking
permission to impact additional wetlands that lay scattered across the
property. In 1999, after considerable negotiation, the Corps of Engineers
approved a second permit that allowed for up to sixty acres to be filled.
The mitigation plan for this permit included the creation and transfer
of 195 acres of new wetlands but allowed areas designated for storm
water run-off - retention ponds - that were already provided for in
the revised master plan to satisfy a considerable portion of this requirement.
The plan was subsequently implemented through the transfer of approximately
221 acres of retention ponds and other newly created wetlands to a non-profit
property owners association. However, both before and after the
second 404 permit was issued the Normans had been engaged in selling
portions of the property to third party developers and others. When
the 1999 permit was issued the Normans retained ownership of only 716
acres of the original parcel.
Lawsuit
and Subsequent Appeal
In 1995, following the approval of their first 404 permit application,
the Normans brought suit in the Court of Federal Claims. The complaint
charged that their 1988 purchase agreement with Southmark for 470 acres
was based upon the Corps of Engineers 1988 delineation and that
the net increase in jurisdictional wetlands between the 1988 and 1991
delineations located within that 470-acre parcel - approximately seventy
acres - represented a taking.
The subsequent procedural history of the suit is long and tortuous.
In 2001 the complaint was amended to include an illegal exaction claim1
that was eventually dismissed by the trial court for lack of jurisdiction.
By November 2003 the case was finally ready to go to trial. The Normans
then moved to retroactively amend their complaint to increase the amount
of the alleged taking from seventy acres to 221 acres - the full amount
they had transferred to the property owners association. The motion
to amend was granted on the first day of trial. Following conclusion
of the trial the court issued an opinion and order denying all of the
Normans takings claims and dismissing their amended complaint.
The Normans appealed the trial courts rulings on their takings
claims as well as their illegal exaction claim to the U.S. Court of
Appeals, Federal Circuit. Their appeal essentially argued that the trial
court had erred by failing to consider that the Corps of Engineers
revocation of the 1988 delineation and subsequent issuance of the 1991
delineation set into motion a chain of events that culminated in the
taking of the 221 acres nearly ten years later, thus rendering their
takings claims meritorious.
As to the dismissed illegal exaction claim, the Normans argued that
the Corps of Engineers 1991 delineation had violated the Energy
and Water Development Appropriations Act of 1992 (EWDA),2
which forbade the expenditure of public funds for delineations using
the Corps 1989 Wetland Delineation Manual. Since the 1991 delineation
had led, according to the Normans, foreseeably and predictably
to the 221-acre mitigation, and since that mitigation constituted an
exaction in return for the Corps approval of the Normans
second 404 permit application, the exaction occurred in violation of
a federal statute, thus bringing the illegal exaction claim under the
subject matter jurisdiction of the Court of Federal Claims.
The
Appeals Courts Analysis
The appeals court noted from the outset of its analysis that the Normans
takings claims did not challenge the governments legitimate authority
to require mitigation in return for granting approval to impact wetlands
or waters of the U.S. over which the Corps has jurisdiction. Rather,
the Normans essential argument was that the entire sequence of
events from the issuance of the first Corps of Engineers delineation
in 1988 to the transfer of the 221 acres in 1999 should be considered
as a single event since the 1991 delineation directly and ineluctably
caused them to lose 221 acres of property.
The court found this argument unconvincing. It pointed out that the
appellants did not even acquire the majority of the 221 acres set aside
under the 1999 mitigation plan until 1994. The court expressed the opinion
that [t]he causal relationship between the revocation of the 1988
Delineation and the appellants alleged loss is simply too attenuated
to support the weight the Normans place on it.3
This conclusion alone, according to the court, was sufficient to dispense
with the bulk of the appellants takings claims.
Nevertheless, the court proceeded to provide a detailed analysis of
the Normans arguments - and why they had to fail. First, the court
considered the Normans claim that the 1999 permit constituted
a physical taking because it required the Normans to transfer title
to the 221 acres to a third party. In fact, the permit did not specifically
require such a transfer; it only required the Normans to record the
formation of a Corps approved funding mechanism for the long term
maintenance of the mitigation and preserve areas. Transferring
the property to a conservation group or non-profit property owners
association was one such mechanism that the Corps approved. There were
other options available to the Normans; they voluntarily chose to transfer
the property. Thus it was plainly evident to the court that the transfer
could not be the basis for a successful physical takings claim.
Continuing with its analysis, the court opined that even if the transfer
could be characterized as a physical taking, the Normans claim
for compensation would fail since the U.S. Supreme Court has held that
a land use regulation does not effect a taking if it substantially
advances legitimate state interests and does not deny an owner economically
viable use of his land provided that there is an essential
nexus between the permit condition and the legitimate state interest.4
The appeals court here agreed with the lower court that in this case
the public interest served
relate[d] directly to the condition
imposed.5
Moreover, since the property conveyed was essentially all earmarked
as storm water run-off storage areas by the Normans master development
plan, the transfer of that property did not impact its economically
viable use to any appreciable degree.6 As to
the appellants categorical takings claim, the court cited binding
and persuasive precedent that a regulatory taking becomes categorical
only if the owner is deprived of all beneficial use of the parcel
as a whole.7 Since the trial court had considered
the entire 2,280 acres to constitute the parcel as a whole,
and since the Normans appeal had not challenged the trial courts
analysis on this point, appellants cannot dispute that courts
conclusion that the facts here do not sustain a categorical takings
claim.8
The court considered the Normans regulatory taking claim arguments
under the three factor balancing test provided by the U.S. Supreme Court
in Penn Central Transp. Co. v. New York City.9 In Penn Central the Supreme
Court defined these three factors as: (1) the extent to which
the regulation has interfered with
reasonable investment-backed
expectations; (2) the economic impact of the regulation on the claimant;
and (3) the character of the governmental action at issue.10
Reviewing the trial courts findings of fact under the deferential
clearly erroneous standard, the appeals court here found
that the trial court was correct in its conclusion that the Normans
had a reasonable investment-backed expectation with respect to only
four of the 221 acres in dispute. Moreover, although a takings claim
is not barred by the mere fact that title was acquired after the
effective date of the state-imposed restriction, the fact that
the Normans were actually and constructively aware of the restrictions
imposed by the 1991 delineation prior to their purchase of the other
1,800 acres of property made it difficult to show that they had bought
their property in reliance on a challenged regulatory scheme.11
Here too the court found the appellants arguments of regulatory
taking to be unpersuasive.
Finally, in considering the appellants illegal exaction claim
the court found that the lower court lacked subject matter jurisdiction
based on the fact that the EWDA was merely an appropriations act and
that, as such, the supposed exaction could not have been due to
a misapplication of the statute as required by the controlling
case law.12 The court also observed that invoking
federal claims court jurisdiction in these circumstances was conditioned
on a demonstration by the appellants that the supposed exaction occurred
as a direct result of the application of the EWDA, a showing
that the Normans failed to make with sufficient verity.13
Even if the Normans could have successfully demonstrated that an illegal
exaction had occurred as a direct result of the misapplication of the
EWDA, that statute does not provide, either directly or by implication,
any cause of action for its violation with a remedy for money damages.
Conclusion
The Court of Appeals, Federal Circuit upheld the Court of Federal Claims
ruling that the conditions on the Normans wetlands fill permit
did not constitute a physical, categorical, or regulatory taking of
their property by the government, and that the Court of Federal Claims
did not have subject matter jurisdiction over appellants claim
that the property conveyed constituted an illegal exaction.
ENDNOTES
1. An exaction is a wrongful demand of a reward
or fee for an official service performed in the normal course of duty.
Blacks Law Dictionary 238 (Bryan A. Garner ed., pocket
ed., West 1996).
2. Pub. L. No. 102-104 (1991).
3. Norman v. U.S., 429 F.3d 1081, 1088
(Fed. Cir. 2005).
4. Id. at 1090 (citing Nollan v. California
Coastal Commn., 483 U.S. 825, 834 (1987), and Dolan v. City of
Tigard, 512 U.S. 374, 386 (1994)).
5.
Id.
6. Id. (citing Norman v. U.S.,
63 Fed. Cl. 231, 261 (Fed. Cl. 2004)).
7.
Id. (citing cases).
8. Id.
9. 483 U.S. 104 (1978). Unlike a physical taking, in
which the government takes actual physical control of property, a regulatory
taking is merely a reduction in the value of a property resulting from
a government regulation.
10.
Id. at 124.
11. Norman, 429 F.3d at 1093 (citing Cienega Gardens
v.U.S., 331 F.3d 1319, 1345-46 (Fed. Cir. 2003)).
12. Id. at 1095 (internal citations omitted).
13.
Id. at 1096.
|
|