| SandBar Printer-Friendly Article |
|---|
SandBar 7:2, July, 2008 Department Lacked Authority to Regulate under State's Shoreline Management Act Twin Bridge Marine Park, LLC v. Dep’t
of Ecology,
162 Wn.2d 825 (Wash. 2008).
Terra Bowling, J.D.
The issue of regulatory authority over coastal
development permits in Washington State came to a head over the
construction of a dry-storage marina. The Supreme Court of
Washington ruled that local governments have the exclusive
authority to approve substantial development permits (SDP).
Furthermore, the only recourse for the State Department of Ecology
to challenge an SDP is through the Washington Land Use Petition Act
(LUPA)
. Background
The Washington State Shoreline Management Act
(SMA) regulates development on state shorelines. Under the SMA,
local governments must develop
shoreline management plans (SMP) that
are approved by the Department. The counties then have the primary
responsibility for administering the permit program and ensuring
compliance with their SMPs. In 1975, Skagit County, Washington approved a final environmental impact statement (FEIS) for Twin Bridge Marine Park, LLC,
to construct an office, a warehouse, and marine facilities on its
property. In 1982, the county issued two shoreline SDPs to Twin
Bridge for the development. The company later decided to convert
its business into a dry-storage marina, and, in 2000, the county
issued an FEIS addendum to the 1975 FEIS, determining that the
dry-land marina development would not have a significant adverse
impact on the environment. The county issued two amended building
permits for the project. The city of Anacortes appealed the permits
under LUPA, but the Department did not join in the appeal.
After Twin Bridge began construction, the
Department issued a stop work order and ordered the company to
obtain a new substantial development shoreline permit. When the company did not stop construction, the Department issued a $17,000 penalty. The company
appealed the decision to the Shorelines Hearings Board (Board).
Skagit County subsequently reevaluated the project and decided to
require new SDPs and suspended the amended building permits. Twin
Bridge stopped work on the project.
After applying to the county for new permits,
the company reached a settlement agreement in which the Department
withdrew its penalty. The company also reached a separate agreement
with the county and Anacortes with regard to the LUPA challenge.
The county then reinstated the
building permits and Twin Bridge resumed construction. The county issued a final shoreline permit incorporating local,
state, and federal permits for the site. The Department refused to
recognize the permits, reinstated the penalty of $17,000 and tacked
on an additional $17,000 penalty. Despite this,Twin Bridge completed construction and opened for business. The Department then issued a
third, $25,000 penalty. Twin Bridge appealed the penalties to the
Board, which upheld the penalties.
On appeal, the
superior court reversed the Board’s decision, finding that
the county’s issuance of the building permits and the FEIS
addendum resulted in county authorization for the project.
Furthermore, an additional permit from the Department was not
necessary, since the county had concluded that the project was in
compliance with the Shoreline Management Act (SMA). And, finally,
the Department could not penalize projects with valid county
permits without first filing a LUPA challenge. In effect, the
Department’s issuance of penalties resulted in an invalid
collateral attack on the county’s decision.
The Washington Court of Appeals affirmed the ruling. The Department appealed the decision to the Washington State Supreme Court. The key issue considered on appeal was whether the Department could impose penalties under the SMA when the project had been constructed pursuant to valid county permits. Authority under the SMA
First, the court noted that the SMA does not
give the Department the authority to directly review a local
government’s decision to issue an SDP. However, the
Department may review other permits under the SMA, such as a
conditional use permit. The Department argued that the dry-land
marina exceeded the impact foreseen by the original permits, and,
thus, the county wrongly concluded that SDPs were the appropriate
permits. The court disagreed, finding that “it is
counterintuitive that a dry-storage facility would have more
shoreline impact than a water marina.” Additionally, because
the county had two EISs it had the best available information for
determining the appropriate permit. For those reasons, the court
found that the county’s characterization of the permits would
control.
Next, the court turned to the issue of whether the Department had the authority to impose penalties on Twin Bridge. The Department cited provisions of the SMA that allow it to impose fines on those who develop in shoreline areas without the proper permits. The court noted that the company had constructed the marina only after reaching an agreement with the Department that it would apply for a new SDP and then obtaining those permits. In this instance, the court found that Twin Bridge had obtained all of the necessary permits, and the Department could not impose penalties on the company. LUPA
The court turned to the Department’s
regulatory authority over local governments regarding shoreline
development. Relying on an analogous case, Samuel’s Furniture v. Department of Ecology,1 the court noted that under the SMA, a local government and not the
Department makes the threshold determination of what shoreline SDPs
are required under the county’s SMP. In Samuel’s Furniture, the
court had determined that LUPA provided the appropriate means for
entities challenging a final land use decision by a local
authority. The court found that the Department was required to
comply with LUPA in this instance as well, given that this was a
final land use decision issued by a local authority, Skagit County.
LUPA stipulates that no “person”
– including entities like the Department – is exempt
from its provisions when challenging a final land use decision by a
local authority with jurisdiction. LUPA requires those opposing a
final land use decision to appeal that decision within twenty-one days. In this instance, the Department had notice of the county’s decision
and did not appeal. After twenty-one days elapsed, the permits were
valid and Twin Bridge correctly relied on them.
Conclusion
The court concluded that the disagreement with
the local permitting authority should have been resolved through
LUPA and not through penalties assessed on Twin Bridge.2 The court
affirmed the lower courts’ decisions and dismissed the
Department’s fines and orders
Endnotes
|
Phone (662) 915-7775 • Fax (662) 915-5267 • 256 Kinard Hall, Wing E, University, MS 38677-1848 |