See individual team reports (Academic Structure, Student Administration, Student Accounting, Reporting, Web / Interfaces, Organizational Readiness, Technology Infrastructure) for additional detail.
There are no significant accomplishments/activities to report for this time period. Team progress was stymied because two members were in Germany for testing, and two members were involved in the aftermath of the 2002 spring semester registration.
One team member was involved in a cursory review of the fee distribution program. A revised proposal to eliminate the Turner Center registration process was developed during this time. The proposal will be presented at the Team Leads meeting on 01/22/2002.
Operating system software, JDK, and a database are being installed on the payment gateway (TouchNet) server.
CRT 8 was applied to production (UMPRD) on 01/19/02. This was originally scheduled for 02/04 but requirements related to CM data entry and end of year processing dictated a date change. CRT 9 has been applied to the CM sandbox. (UMTST)
Work continues on defining authorizations, and adjusting the environments as applicable.
Over the next two months many upgrades are planned on the SAP landscape ard there are downtimes scheduled most Fridays and Saturdays. Please check the calendar at http://ts.olemiss.edu/webcal/webcal.pl when scheduling activities to verify availability.