See individual team reports (Academic Structure, Student Administration, Student Accounting, Reporting, Web / Interfaces, Organizational Readiness, Technology Infrastructure) for additional detail.
Veena has updated the new proposed eforms course add/change form. The eform is being reviewed by several groups to ensure that it meets both the needs of the academic community and CM use.
A list of all degrees missing from CM has been reviewed. Some information on these degrees needs to be checked (e.g. exact titles) before requests are made to the departments to complete the listings in CM.
Due to probable limitations on entering academic history for all transfer students, prerequisite and corequisite checking for the upcoming March 2003 registration will probably not be enforced. Work is still continuing to have all the required prerequisite and corequisite information entered into CM before March even though enforcement of these may not be possible.
Work continues on finalizing the fee procedures and documenting the configuration and routines that have been developed. We continue to collect information for the interfaces.
Our work continues on print workbench and correspondence.
We experienced from problems with FM, which slowed our progress during this reporting period. Some fixes for the FM problems were recently installed in the sandbox, and we will test the fixes as soon as possible. We have worked on some data mapping between student master data and business partner data. We tested some cash at desk functionality, and we documented the IMG tables involved in handling incoming/outgoing payment processing.
The team made progress on solving the issue of converting outstanding balances in the legacy system to open items in SAP.
Next upgrade cycle for the production landscape
UMDEV - 08/30/02
UMQAS - 09/06/02
UMPRD - 09/21/02
The following will be applied.
HR SP 51-54
R/3 SP 33-34
BASIS SP 34-35
Application Interface SP 34-35
HR Public Sector (HRPS) Patch 12, 13
Campus Management Patches 5, 6
BSI TUBs 150-160
The necessary software for Biller Direct has been received and planning is underway for the installation.